Planned Maintenance - Mumbai (Cluster C)
Scheduled Maintenance Report for Forcepoint Cloud Status
Completed
The scheduled maintenance has been completed.
Posted Dec 08, 2024 - 19:54 UTC
Update
Maintenance activity continues as expected; however, we are extending the maintenance window by 2 hours
Posted Dec 08, 2024 - 18:50 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 08, 2024 - 14:15 UTC
Scheduled
Forcepoint is extending the maintenance activity in Mumbai data center. While majority of the planned work has been completed successfully, we are performing a thorough validation of all infrastructure components and services before re-introducing the services back to Mumbai data center.

Web Security traffic has been re-introduced back to Mumbai, however vPoP, Hybrid and IPSEC/GRE tunnel connections remains failed over to alternate locations. We will provide further update as we start moving the remaining services back to Mumbai.
Posted Dec 08, 2024 - 14:08 UTC
This scheduled maintenance affected: Data Centers and PoP (Mumbai (C)).