Planned Maintenance - Singapore (Cluster R) Datacenter

Scheduled Maintenance Report for Forcepoint Cloud Status

Completed

The scheduled maintenance has been completed.
Posted Feb 17, 2025 - 03:43 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 14, 2025 - 10:00 UTC

Scheduled

Forcepoint will be conducting a planned maintenance in our Singapore (Cluster R) Datacenter on Friday, February 14th at 10:00 UTC for approximately 72 hours. The maintenance activity will involve certain changes for further enhancing our network infrastructure to provide improved performance to our Cloud services.

We anticipate minor loss of connectivity for brief moment while customer traffic is failed over to an alternate datacenter. Customers are requested to ensure that they have redundant IPSEC and GRE tunnels configured to a redundant data center to ensure seamless failover of tunnel traffic.

We apologize for any inconvenience this may cause and appreciate the cooperation.
Posted Feb 12, 2025 - 22:00 UTC
This scheduled maintenance affected: Data Centers and PoP (Singapore (R)).