Forcepoint will be performing a planned maintenance activity in our Toronto Data Center (Cluster-YYZA) on Sunday, April 19th, starting at 02:30 UTC for 3 hours. The maintenance activity will involve performing an upgrade of our NGFW appliances.

The upgrades will be performed on one appliance at a time, so we do not anticipate any loss of connectivity for customers connecting to Toronto via IPSEC or GRE tunnels.

We appreciate your understanding and cooperation as we continue to enhance our infrastructure.
Posted Apr 16, 2026 - 03:44 UTC